Featured Image

Phase I Projects & Status Updates

Phase I of our Capital Improvement Bond was completed in August 2019. Statuses in GREEN indicate the project has been completed. Pictures of select projects have been posted in the photo gallery below.

Current Status: Completed
Last Updated: Friday, November 13, 2020

Comsewogue High School

  • Kitchen Ceiling Replacement: COMPLETED

  • Security Vestibule: COMPLETED

  • Cafeteria Ceiling and Lighting Replacement: COMPLETED

  • Interior Doors Locksets to Meet ADA Compliance: COMPLETED

  • Re-Balance and Upgrade Main Office Ductwork and Controls: COMPLETED

  • Remove & Replace 12 Interior Door Hold-Open Devices: COMPLETED

JFK Middle School

  • Security Vestibule & Front Entry Replacement: COMPLETED

  • Kitchen Ceiling Replacement: COMPLETED

  • Interior Doors Locksets to Meet ADA Compliance: COMPLETED

  • Skylight Protection and Replacement: COMPLETED

  • Add Missing Closers to Corridor Doors: COMPLETED

  • Provide Fresh Air Intake in Rooms 205A, 103, 224: COMPLETED

  • Replace Exterior Doors & Frames: COMPLETED

  • Replace 1 Skylight / Add Fall Protection to All Skylights: COMPLETED

Boyle Road Elementary School

  • Parking Lot and Sidewalk Replacement: COMPLETED

  • Security Vestibule: COMPLETED

  • Interior Doors Locksets to Meet ADA Compliance: COMPLETED

  • Ventilation Upgrades for Music Rooms: COMPLETED

  • Gas Conversion and Cooled Condenser: COMPLETED

  • Replace & Add Door Closers to 10 Interior Doors: COMPLETED

  • Repair Vandalized Rooftop Penthouse and Provide Guards: COMPLETED

  • Provide District-Wide Portable Lift for Stage Access: COMPLETED

  • Provide Booster Bump for Kindergarten Wing: COMPLETED

Terryville Road Elementary School

  • Cafeteria Floor Replacement: COMPLETED

  • Parking Lot and Sidewalk Replacement: COMPLETED

  • Security Vestibule: COMPLETED

  • Interior Doors Locksets to Meet ADA Compliance: COMPLETED

  • Kitchen Walk-In Cooler: COMPLETED

  • Replace & Add Door Closers for 10 Doors: COMPLETED

  • Provide Fresh Air Intake for 2 Stage Heating & Ventilation Units: COMPLETED

Clinton Avenue Elementary School

  • Security Vestibule: COMPLETED

  • Interior Doors Locksets to Meet ADA Compliance: COMPLETED

  • Gas Conversion and Cooled Condenser: COMPLETED

  • Kitchen Ceiling Replacement: COMPLETED

  • Replace & Add 10 Door Closers:COMPLETED

  • Provide Fresh Air Intake for Old Bookroom: COMPLETED

  • Replace 6 Exterior Doors & Frames:COMPLETED

Norwood Avenue Elementary School

  • Security Vestibule: COMPLETED

  • Interior Doors Locksets to Meet ADA Compliance: COMPLETED

  • Kitchen Ceiling Replacement: COMPLETED

  • Kitchen Serving Line Reconfiguration: COMPLETED

  • Door Replacements: COMPLETED

  • Add Missing Closers to Corridor Doors: COMPLETED

  • Provide Fresh Air Intake for Primary Project and 2 Speech Rooms: COMPLETED