2018 Capital Improvement Bond

About the Capital Improvement Bond

During the March 5, 2018 meeting of the Comsewogue School District Board of Education, the board voted unanimously to move forward with a bond proposal to improve district facilities based on recommendations from the community-led Facilities Committee. The Facilities Committee was established to review the state-mandated five-year building conditions survey, tour district buildings, review financial and enrollment data, and, ultimately, present its recommendations and findings to the board. The committee presented its recommendations in a special public meeting on February 12, 2018. The proposal, as recommended by the committee, and now approved by the Board of Education, passed in a community vote on May 15, 2018. Residents within the Comsewogue School District approved both the district’s bond and 2018-2019 budget. Voters approved the bond: 768 YES to 315 NO votes and the budget 829 YES to 263 NO.

The proposed bond, totaling $32 million, focuses on improving three main areas throughout the district's six school buildings: health and safety, infrastructure and the three A's - academics, arts and athletics. The proposed facility improvements preserve the integrity of the school buildings, address repairs, improve instructional resources for all and upgrade athletic facilities. The bond proposal includes several projects, including: creating security vestibules at the main entrances of all buildings, updating casework in all buildings, renovating auditorium seating and carpeting and updating the sound system and rigging at John F. Kennedy Middle School, and replacing the press box and bathroom/concession stand at the high school's main athletic field.

Projects have been categorized by importance and urgency, and broken into two groups: A-list items and B-list items. If approved by residents on May 15, items on the A-list, which have been categorized as high priority, will receive priority. Following the completion of the A-list items, B-list items will be re-prioritized based on available funds and need. A full list of the proposed projects is available below.

"We are grateful to our community for their continued support of our schools and our students,” said former Superintendent of Schools Dr. Joseph Rella. “Their approval of the bond and 2018-2019 budget will enable us to enhance and enrich health and safety, infrastructure and the three A’s – academics, arts and athletics."

Status Updates

  • Current Status: Completed
    Last Updated: Friday, November 13, 2020

    Comsewogue High School
    • Kitchen Ceiling Replacement: COMPLETED
    • Security Vestibule: COMPLETED
    • Cafeteria Ceiling and Lighting Replacement: COMPLETED
    • Interior Doors Locksets to Meet ADA Compliance: COMPLETED
    • Re-Balance and Upgrade Main Office Ductwork and Controls: COMPLETED
    • Remove & Replace 12 Interior Door Hold-Open Devices: COMPLETED
    JFK Middle School
    • Security Vestibule & Front Entry Replacement: COMPLETED
    • Kitchen Ceiling Replacement: COMPLETED
    • Interior Doors Locksets to Meet ADA Compliance: COMPLETED
    • Skylight Protection and Replacement: COMPLETED
    • Add Missing Closers to Corridor Doors: COMPLETED
    • Provide Fresh Air Intake in Rooms 205A, 103, 224: COMPLETED
    • Replace Exterior Doors & Frames: COMPLETED
    • Replace 1 Skylight / Add Fall Protection to All Skylights: COMPLETED
    Boyle Road Elementary School
    • Parking Lot and Sidewalk Replacement: COMPLETED
    • Security Vestibule: COMPLETED
    • Interior Doors Locksets to Meet ADA Compliance: COMPLETED
    • Ventilation Upgrades for Music Rooms: COMPLETED
    • Gas Conversion and Cooled Condenser: COMPLETED
    • Replace & Add Door Closers to 10 Interior Doors: COMPLETED
    • Repair Vandalized Rooftop Penthouse and Provide Guards: COMPLETED
    • Provide District-Wide Portable Lift for Stage Access: COMPLETED
    • Provide Booster Bump for Kindergarten Wing: COMPLETED
    Terryville Road Elementary School
    • Cafeteria Floor Replacement: COMPLETED
    • Parking Lot and Sidewalk Replacement: COMPLETED
    • Security Vestibule: COMPLETED
    • Interior Doors Locksets to Meet ADA Compliance: COMPLETED
    • Kitchen Walk-In Cooler: COMPLETED
    • Replace & Add Door Closers for 10 Doors: COMPLETED
    • Provide Fresh Air Intake for 2 Stage Heating & Ventilation Units: COMPLETED
    Clinton Avenue Elementary School
    • Security Vestibule: COMPLETED
    • Interior Doors Locksets to Meet ADA Compliance: COMPLETED
    • Gas Conversion and Cooled Condenser: COMPLETED
    • Kitchen Ceiling Replacement: COMPLETED
    • Replace & Add 10 Door Closers: COMPLETED
    • Provide Fresh Air Intake for Old Bookroom: COMPLETED
    • Replace 6 Exterior Doors & Frames: COMPLETED
    Norwood Avenue Elementary School
    • Security Vestibule: COMPLETED
    • Interior Doors Locksets to Meet ADA Compliance: COMPLETED
    • Kitchen Ceiling Replacement: COMPLETED
    • Kitchen Serving Line Reconfiguration: COMPLETED
    • Door Replacements: COMPLETED
    • Add Missing Closers to Corridor Doors: COMPLETED
    • Provide Fresh Air Intake for Primary Project and 2 Speech Rooms: COMPLETED
  • Current Status: Completed
    Last Updated: Friday, April 16, 2021

    Comsewogue High School
    • Renovation of Faculty Bathrooms and Nurse's Bathrooms to Meet ADA Compliance: COMPLETED
    • Replace Cafeteria Windows, Storefront and Tech Room Windows: COMPLETED
    • Replace Waterless Urinals and Sinks: COMPLETED
    • Add Remaining RUT and HVAC Units to BMS: COMPLETED
    • Install Batting Cage for Upper Gym: COMPLETED
    • Expansion of Project Adventure Elements: COMPLETED
    • Brickwork: COMPLETED
    • Masonry Repairs & Add Stainless Steel Cap at Chimney: COMPLETED
    JFK Middle School
    • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED
    • Reconnect leaders to pools at recess area: COMPLETED
    • Add Electrical Circuits for Air Conditioning: COMPLETED
    • Replace Auditorium Seating: COMPLETED
    • Replace Carpet in Auditorium: COMPLETED
    • Provide a Permanent Sound System in Auditorium: COMPLETED
    • Repair CMU: COMPLETED
    • Replace Hallway Ceilings: COMPLETED
    • Provide infill at Railing in Boiler Room: COMPLETED
    Boyle Road Elementary School
    • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED
    • Provide additional Exterior Lighting: COMPLETED
    • Replace all Waterless Urinals and Sinks: COMPLETED
    • Repair and Replace Drainage in 1 Boys Bathroom: COMPLETED
    • Regrade back pitch at South and Southwest: COMPLETED
    • Provide infill mesh at Boiler Room Railing: COMPLETED
    • Add Circuits to Cafeteria, Kitchen and Gym Area: COMPLETED
    • Replace 3 Exterior Light Poles: COMPLETED
    • Replace Railings and Tread Nosings at Loading Dock Stairs: COMPLETED
    • Repair Crack at Retaining Wall: COMPLETED
    • Add 2 Pole-Mounted Lights and Structures in South Parking Lot: COMPLETED
    Terryville Road Elementary School
    • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED
    • Add Circuits for Air Conditioning Units: COMPLETED
    • Brickwork: COMPLETED
    • Tuck-point Chimney: COMPLETED
    • Roof Replacement: COMPLETED
    • Add Boiler Room to Generator: COMPLETED
    • Add Drainage at Rear Drive: COMPLETED
    • Add Spare Electrical Panels: COMPLETED
    • Replacement of PA/Intercom System: COMPLETED
    • Replace Waterless Urinals and Sinks: COMPLETED
    Clinton Avenue Elementary School
    • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED
    • Repair and Replace Asphalt / Mill Top Course of Asphalt: COMPLETED
    • Repair and Add Exterior Lighting in Rear of Building: COMPLETED
    • Replace Waterless Urinals and Sinks: COMPLETED
    • Replace Sidewalks: COMPLETED
    • Provide infill mesh at Boiler Room Railing: COMPLETED
    • Replace Student Wardrobes / Storage Units: COMPLETED
    Norwood Avenue Elementary School
    • Replace Elevator Controls and Hydraulics: COMPLETED
    • Renovate Faculty Bathrooms to Meet ADA Compliance: COMPLETED
    • Repairs to Parking Lot: COMPLETED
    • Replace Asphalt at District Office Parking Lot: COMPLETED
    • Add Additional Parking for Pre-K Program: COMPLETED
    • Replace Sidewalks: COMPLETED
    • Install additional Electrical Outlets in Classrooms: COMPLETED
    • Repair Roof Drain: COMPLETED
    • Replace Waterless Urinals and Sinks: COMPLETED
    • Repair Loading Dock: COMPLETED
    • Replace Student Wardrobes / Storage Units: COMPLETED
    • Brickwork: COMPLETED
    • Masonry Repairs & Add Stainless Steel Cap at Chimney: COMPLETED
    • Repair CMU Cracks: COMPLETED

     

  • Current Status: Completed
    Last Updated: Wednesday, July 26, 2023

    Comsewogue High School

    • Interior Renovations of 2 Art Rooms: COMPLETED
    • Install Carbon Monoxide Detectors: COMPLETED
    • Parking Lot, Sidewalk and Curb Replacement: COMPLETED
    • Repair CMU Cracks: COMPLETED
    • New Field House (Press Box, Bathrooms and Concession Stand): COMPLETED

    JFK Middle School

    • Install Carbon Monoxide Detectors: COMPLETED
    • Parking Lot, Sidewalk and Curb Replacement: COMPLETED
    • Brickwork: COMPLETED
    • Masonry Repairs & Add Stainless Steel Cap at Chimney: COMPLETED
    • Replace Classroom and Lobby Ceilings & Lighting: COMPLETED
    • Replace Waterless Urinals and Sinks: COMPLETED
    • Replace Perimeter Chain Link Fence Along Terryville Road: COMPLETED

    Boyle Road Elementary School

    • Interior Renovation of Art Room: COMPLETED
    • Install Carbon Monoxide Detectors: COMPLETED
    • Replace Caulk and Tuck-point Brick: COMPLETED
    • Masonry Repairs & Add Stainless Steel Cap & Chimney: COMPLETED
    • Re-caulk Windows and Sills: COMPLETED
    • Upgrade Electrical Service: COMPLETED
    • Repair Interior CMU Cracks: COMPLETED
    • Replace Stage and Cafeteria Sound System: COMPLETED

    Terryville Road Elementary School

    • Interior Renovation of Art Room: COMPLETED
    • Install Carbon Monoxide Detectors: COMPLETED
    • Upgrade Electrical Service: COMPLETED
    • Repair CMU Cracks: COMPLETED
    • Replace Main Office Rooftop Air Conditioning: COMPLETED
    • Replace Domestic Hot Water Heater: COMPLETED
    • Add Solar Panels to Roof: COMPLETED

    Clinton Avenue Elementary School

    • Install Carbon Monoxide Detectors: COMPLETED
    • Add Receptacles to Classrooms and Hallways: COMPLETED
    • Replace caulk and tuck-point brickwork: COMPLETED
    • Masonry Repairs & Add Stainless Steel Cap at Chimney: COMPLETED
    • Reset and Caulk Stone Sills: COMPLETED
    • Replace Window Caulking: COMPLETED
    • Repair CMU Cracks: COMPLETED

    Norwood Avenue Elementary School

    • Install Carbon Monoxide Detectors: COMPLETED
    • Replace Roof Above District Office: COMPLETED

     

  • Current Status: Completed
    Last Updated: Tuesday, November 21, 2023

    Comsewogue High School

    • Upgrades to Electrical Service: COMPLETED
    • Carbon Monoxide Detectors: COMPLETED

    JFK Middle School

    • Renovations to Art & F&CS Classrooms: COMPLETED
    • Replace Stage Rigging: COMPLETED

    Boyle Road Elementary School

    • Replace Casework and Cabinets in Classrooms: COMPLETED

    Terryville Road Elementary School

    • Replace Casework and Cabinets in Classrooms: COMPLETED

    Norwood Avenue Elementary School

    • Upgrades to Electrical Service: COMPLETED
    • Replace Classroom Ceilings: COMPLETED
    • Replace Cafeteria Ceiling: COMPLETED